Project Overview

The Pilgangoora mine site is a lithium processing plant owned and operated by Pilbara Minerals. Westforce was engaged to complete all civil and structural works associated with the Spodumene Filter 2 Building, Spodumene Filter 2 Feed Area, Spodumene Cloth Wash Tank, Coarse Spodumene Storage Slab, Compressor Shed, Pre-Flotation civil works (Area 23500), and the HMS Bypass Valve Platform (Area 22200). These works supported the expansion of the site’s lithium processing capacity.

  • Spodumene Filter 2 Building: Ground slab, walls, pedestals, suspended slab, and topping slabs.
  • Spodumene Filter 2 Feed Area & Cloth Wash Tank: Tank ring beam, ground slab, and pedestals.
  • Coarse Spodumene Storage Slab & Air Compressor Shed: Ground slab, footings, and roller kerb.
  • HMS Bypass Valve Platform: Footings and pedestals.
  • Pre-Flotation Structure: Demolition of existing kerbs, installation of ring beam, ground beams, ground slab, pedestals, and new kerbs.
  • General Works: Excavation and trenching for buried services and conduits, ground preparation for concrete structures, and installation of earthing terminals.

Concrete: 550m³ ~
Steel Reinforcement: 80T ~
Detailed Earthworks: 850³ ~

Location

Value

$1M – $5M ~

Client

SIMPEC

Completion Year

2022
Project Overview

The Pilgangoora mine site is a lithium processing plant owned and operated by Pilbara Minerals. Westforce was engaged to complete all civil and structural works associated with the Spodumene Filter 2 Building, Spodumene Filter 2 Feed Area, Spodumene Cloth Wash Tank, Coarse Spodumene Storage Slab, Compressor Shed, Pre-Flotation civil works (Area 23500), and the HMS Bypass Valve Platform (Area 22200). These works supported the expansion of the site’s lithium processing capacity.

  • Spodumene Filter 2 Building: Ground slab, walls, pedestals, suspended slab, and topping slabs.
  • Spodumene Filter 2 Feed Area & Cloth Wash Tank: Tank ring beam, ground slab, and pedestals.
  • Coarse Spodumene Storage Slab & Air Compressor Shed: Ground slab, footings, and roller kerb.
  • HMS Bypass Valve Platform: Footings and pedestals.
  • Pre-Flotation Structure: Demolition of existing kerbs, installation of ring beam, ground beams, ground slab, pedestals, and new kerbs.
  • General Works: Excavation and trenching for buried services and conduits, ground preparation for concrete structures, and installation of earthing terminals.

Concrete: 550m³ ~
Steel Reinforcement: 80T ~
Detailed Earthworks: 850³ ~