As part of broader infrastructure upgrades at BHP’s Eastern Ridge operations, Westforce was engaged by Monadelphous to deliver the civil works and installation of a 12km surplus water pipeline.
The system facilitates water transfer across the Ore Body 32 mine area, strengthening site-wide water management and supporting BHP’s environmental compliance objectives.
Executed near Newman in the Pilbara, the project was completed across rugged terrain and variable ground conditions, demonstrating Westforce’s expertise in complex, remote-area delivery.
Trenching: 12km ~
Pipeline Installation: DN600-800 across full alignment, 12km ~
Bulk Earthworks: 7,000m³ ~
Creek Crossing: 6+m deep ~
Clearing and Grubbing: 23Ha ~
Location
Value
Client
Completion Year
As part of broader infrastructure upgrades at BHP’s Eastern Ridge operations, Westforce was engaged by Monadelphous to deliver the civil works and installation of a 12km surplus water pipeline.
The system facilitates water transfer across the Ore Body 32 mine area, strengthening site-wide water management and supporting BHP’s environmental compliance objectives.
Executed near Newman in the Pilbara, the project was completed across rugged terrain and variable ground conditions, demonstrating Westforce’s expertise in complex, remote-area delivery.
Trenching: 12km ~
Pipeline Installation: DN600-800 across full alignment, 12km ~
Bulk Earthworks: 7,000m³ ~
Creek Crossing: 6+m deep ~
Clearing and Grubbing: 23Ha ~