Mining Area C Surplus Water Phase 3

Location

Newman, WA

Value

$10M ~

Client

Monadelphous

Completion Year

2021
Project Overview

The BHP MACSWP3 Dewatering project consists of the construction of the Dewatering Infrastructure at the Area C Iron Ore Mine Site to remove existing water from an exploration area of the mine so BHP could commence mining.

Westforce were contracted to do the civil works required to complete the works required at the MAR transfer tank, the main pipeline and the 8 reinjection MAR bores.

Contact Us

Name(Required)

Careers

Express Your Interest

Name(Required)
Max. file size: 100 MB.
Max. file size: 100 MB.

Enquire Now

Name(Required)