Newman Mining Area C Surplus Water Phase 3

Location

Value

$10M – $15M ~

Client

Monadelphous

Completion Year

2021
Project Overview

The BHP MACSWP3 Dewatering project consisted of the construction of the Dewatering Infrastructure at the Area C Iron Ore Mine Site to remove existing water from an exploration area of the mine so BHP could commence mining.

Westforce were contracted to do the civil works required to complete the works required at the MAR transfer tank, the main pipeline and the 8 reinjection MAR bores.

  • Installation of civil works for 8 bore heads
  • Transfer pipeline
  • Installation and removal of borrow pit
  • Installation of access track
  • MAR transfer tank
  • Concrete repair works
  • Excavation works
  • Formwork
  • Concrete pad and ring beam construction

Concrete: 500m³ ~
Earthworks: 20,000³ ~
Reinforcement: 45T ~

Location

Value

$10M – $15M ~

Client

Monadelphous

Completion Year

2021
Project Overview

The BHP MACSWP3 Dewatering project consisted of the construction of the Dewatering Infrastructure at the Area C Iron Ore Mine Site to remove existing water from an exploration area of the mine so BHP could commence mining.

Westforce were contracted to do the civil works required to complete the works required at the MAR transfer tank, the main pipeline and the 8 reinjection MAR bores.

  • Installation of civil works for 8 bore heads
  • Transfer pipeline
  • Installation and removal of borrow pit
  • Installation of access track
  • MAR transfer tank
  • Concrete repair works
  • Excavation works
  • Formwork
  • Concrete pad and ring beam construction

Concrete: 500m³ ~
Earthworks: 20,000³ ~
Reinforcement: 45T ~