Beenyup AWRP Stage 1 and 2 Soil Remediation

Location

Value

$5M – $10M ~

Client

Water Corporation

Completion Year

2017
Project Overview

Westforce completed the Early Works Contract (EWC) for the Stage 2 development, which carried out site preparation work across the area in advance of the main contract works.

Stage 2 of the Beenyup Advanced Water Recycling Plant (AWRP) was constructed at the Beenyup Wastewater Treatment Plant (WWTP), Western Australia on behalf of the Water Corporation.

  • Installation of temporary retention structures
  • Excavation of stockpiles and uncontrolled fill to varying levels
  • Impact rolling compaction over most of the base of the excavation
  • Low vibration proof compaction
  • Vibration and dust monitoring
  • Conventional proof compaction
  • Handling of excavated materials, including off-site disposal of unsuitable asbestos-contaminated material
  • Replacement with clean fill and compaction of fill to nominated levels

Site Clearing: 18,000m² ~
Asbestos contaminated material: 20,000m³ ~
Bulk Earthworks including Impact Roller Works: 35,000m³ ~

Location

Value

$5M – $10M ~

Client

Water Corporation

Completion Year

2017
Project Overview

Westforce completed the Early Works Contract (EWC) for the Stage 2 development, which carried out site preparation work across the area in advance of the main contract works.

Stage 2 of the Beenyup Advanced Water Recycling Plant (AWRP) was constructed at the Beenyup Wastewater Treatment Plant (WWTP), Western Australia on behalf of the Water Corporation.

  • Installation of temporary retention structures
  • Excavation of stockpiles and uncontrolled fill to varying levels
  • Impact rolling compaction over most of the base of the excavation
  • Low vibration proof compaction
  • Vibration and dust monitoring
  • Conventional proof compaction
  • Handling of excavated materials, including off-site disposal of unsuitable asbestos-contaminated material
  • Replacement with clean fill and compaction of fill to nominated levels

Site Clearing: 18,000m² ~
Asbestos contaminated material: 20,000m³ ~
Bulk Earthworks including Impact Roller Works: 35,000m³ ~