Sandfire Resources’ DeGrussa solar farm and battery energy storage system is at the end of its current off-take agreement. Neoen selected Westforce to manage the decommissioning and rehabilitation of the DeGrussa Solar PV Hybrid Project in Western Australia’s goldfields region.
The project comprised of a 10.6 MW single-axis tracking solar power plant paired with a 4 MW lithium-ion battery storage system.
Westforce’s scope of work included decommissioning, dismantling, and packaging of the solar farm and battery storage facility.
This involved the following:
Panels Removed: 34,080
Solar Farm: 10.6MW
Battery Storage: 4MW
Slew Drive Motors: 426
Scrap Steel: 850T ~
Scrap Copper Cabling: 30T ~
Rehabilitation Area: 240,000m² ~
Location
Value
Client
Completion Year
Sandfire Resources’ DeGrussa solar farm and battery energy storage system is at the end of its current off-take agreement. Neoen selected Westforce to manage the decommissioning and rehabilitation of the DeGrussa Solar PV Hybrid Project in Western Australia’s goldfields region.
The project comprised of a 10.6 MW single-axis tracking solar power plant paired with a 4 MW lithium-ion battery storage system.
Westforce’s scope of work included decommissioning, dismantling, and packaging of the solar farm and battery storage facility.
This involved the following:
Panels Removed: 34,080
Solar Farm: 10.6MW
Battery Storage: 4MW
Slew Drive Motors: 426
Scrap Steel: 850T ~
Scrap Copper Cabling: 30T ~
Rehabilitation Area: 240,000m² ~