Neerabup Ground Water Treatment Plant (GWTP) Upgrade to 150ML (SWJV)

Location

Tamala Park, WA

Value

$(50-60)M

Client

Water Corporation

Completion Year

2021
Project Overview

The Neerabup Groundwater Scheme Treatment Plant (GWTP) currently produces up to 100 ML/d of treated water.

The treated water is distributed by the Clear Water Pumping Station (CWPS) to the Neerabup Reservoir and two major distribution mains.

Water production in excess of zone demand is transferred from Neerabup Reservoir to the larger Wanneroo Reservoir by the Neerabup Transfer Pump Station (NTPS).

The GWTP is currently fed by two bore schemes, the Quinns and Whitfords borefields.

The Neerabup Groundwater Treatment Plant Upgrade will increase the system production up to 150 ML/d.

Four (4) new bores will be constructed in order to abstract the additional flow. In order to treat and deliver this additional volume, upgrades to the existing GWTP, NTPS, CWPS and Neerabup Reservoir are required.

  • Siteworks, demolition and reinstatement
  • Piping, valves and fittings
  • Excavations up to -6m, & backfilling
  • Structural steelwork
  • Concrete works
  • Bulk earthworks
  • Mechanical Install and major piping works
  • 170m3+ wall pours (multiple pumps)
  • Construction of buildings and fit outs
  • Prefabricated tilt-up structures

Concrete Works: 7,500m3 ~
Bulk Earthworks: 50,000m3 ~
MSCL Pipe: 1400d down to 150d – 3000L/M
Stainless Steel Pipe: 600d to 80d – 500L/M
HDPE & HSCR Pipe: 2000 LM
Valves: 1400d to 80d