Location Value Client
Roy Hill Mine Site, Newman WA $7.5M ~ Aerison

PROJECT OVERVIEW

The project is located on the Roy Hill Mine Site, and consists in the construction of a new Saline Water Reverse Osmosis Desalination (SWROD) which will be integrated with the existing Brackish Water Reverse Osmosis (BWRO) to create a Water Treatment System suitable for treating the forecasted water supply and demand conditions in the future.

PROJECT SCOPE

The scope includes bulk earthworks, detailed earthworks, construction of roads and concrete in order for Westforce to construct the new SWROD water treatment system, and associated infrastructure.

The concrete package includes footings, slabs, pedestals, and ring beams for water tanks.

PROJECT STATS

Duration: 36 weeks
Concrete: 1600m3
Bulk Earthworks: 10,000m3
Max Crew Size: 25