Location Value Client
Newman, WA $10M ~ Roy Hill Iron Ore

START: 2022 - FINISH: 2022


PROJECT OVERVIEW

The ROM 4 Project is a 40.5Mtpa facility that is anticipated to deliver first ore by January 2023, and to be in service until 2032.

PROJECT SCOPE

Detailed Earthworks - Foundation preparation, loading, hauling, placement, and compaction of material

Concrete - Supply and installation of reinforced concrete for conveyor CVR523, Crushing Station 5, Transformers, switchrooms & drive-in sumps

Earthing – Installation & testing of earth grids, electrodes, and bonds

Miscellaneous - Light pole footings, grouting, concrete stair pads, and installation of bollards

Concrete works in further detail included:
Footings, slabs, walls, plinths & pedestal, precast panels, reinforcing steel, blinding, formwork, construction joints, hold down bolts, grouting, and all embedded items.

PROJECT STATS

Concrete: 2,600m3
Steel Reinforcement: 370 Tons