Location | Value | Client |
Newman, WA | $10M ~ | Roy Hill Iron Ore |
Roy Hill is currently finalising its mine plans to expand its operation with a new Run of Mine (ROM4).
The ROM4 Project is a 40.5Mtpa facility which is planned to deliver first ore by January 2023, and to be in service until 2032.
The scope includes the concrete and detailed earthworks to allow Westforce to construct Conveyor CVR523 and Crushing Station 5, and associated infrastructure.
The concrete package includes footings, slabs, plinths and pedestals, precast panels, for a total of 2,000m3 of concrete.
Duration: 12 weeks
Concrete: 2,000m3
Steel Reinforcement: 365 Tons
Max Crew Size: 50 workers