Location Value Client
Craigie, WA $5M ~ KEP Recharge Alliance

START: March 2015 - FINISH: June 2016


PROJECT OVERVIEW

Westforce were contracted by the KEP Recharge Alliance (CH2M Hill, Thiess JV) for the design and construction of new 6 new process buildings including a switch room at the AWRP facility, based in Craigie.

 

PROJECT SCOPE

  • Construction of all superstructure elements
  • Electrical works, including design
  • Mechanical works including design
  • Fit-out works including ceilings, doors, windows & flooring
  • Switchrooms (precast concrete construction)
  • Process buildings (structural steel with metal cladding)