Location | Value | Client |
Marble Bar, WA | $10M ~ | Fortescue Metals Group |
PROJECT OVERVIEW
The project involves the construction of new NPI infrastructure, for FMG at their Iron Bridge Mine site. Including but not limited to, HV Tyre Change Warehouse; General Warehouse; HV Workshop; HV Washdown Bay with a HV drive in sump & hydrocarbon storage; and a Welding Workshop.
PROJECT SCOPE
To complete all 4 structures and the washdown the scope will include earthworks 15,000m3 concrete 2500m3, structural steel, domes, containers, electrical, mechanical and office fit out.
PROJECT STATS
Duration: 3.5 months
Max Crew Size: 65